You can use your favorite social network to register or link an existing account:
Or use your email address to register without a social network:
Sign in with these social networks:
Or enter your username and password
Forgot your password?
Yes, please link my existing account with for quick, secure access.
No, I would like to create a new account with my profile information.
Tips
How-to
News
Videos
Stories
The Project Admin Blog
Project Programmability
Microsoft SharePoint
Brian Smith
Christophe Fiessinger
Jan Kalis & Project Partners
projectified
Jack Dahlgren MVP
MS Project Experts
Microsoft EPM Solution, PJ
Ben Howard
Project Home
The Gantt Chart view is the most commonly used view in Project. It lists the tasks in your project, and illustrates their relationship to one another and the schedule using Gantt bars. Let's look a little more closely at each portion of the view.
First, let's take a look at the left portion of the view. This portion uses a table format, and is where each of the tasks, summary tasks, and subtasks in your project are listed. You can use this table toenter new tasks, indent or outdent your existing tasks, set task durations, and identify predecessor tasks.
The right portion of the view illustrates the tasks, dates, and durations across a timeline. You canadjust the timeline units and change the formatting of the bars on the Gantt chart.
For more information about the Gantt Chart view, see Work with the Gantt Chart view. For more information about other views in Project 2007, see Overview of Project views.